Bathroom remodel estimate. Every number shown.
Check the quantities, materials and labor behind a bathroom bid before you commit to an estimating service.
One estimate, $149. Under 1 hour.
That is our planned service. It is not taking jobs yet. This page is a free, complete sample.
412 Elm St bathroom
Made-up address, scope and rates. No plans or photos were uploaded.
Sample estimate total
$14,860.00
12 line items · 104 hr · $65.00/hr labor
20% markup on materials and labor · ZIP 30301
The job behind the number.
Scope notes
Gut and replace an 8 × 10 ft bathroom with an 8 ft ceiling. Keep the existing fixture layout.
Install a tub, tiled surround, tile floor, vanity and toilet. Replace the fan and light, then paint and trim.
Sample rates, not local pricing
Labor is $65.00/hr for every line item. Markup is 20% of materials plus labor, not a 20% margin.
ZIP 30301 is an example only. Material prices and hours are illustrative allowances, not supplier prices or measured production rates.
The complete takeoff.
Material total = quantity × unit cost. Labor total = hours × $65.00. Line total = materials + labor.
Quantities are installed amounts. Tile unit costs include the stated waste allowance; do not add waste again.
| Line item / quantity basis | Quantity | Material / unit | Materials | Labor hr | Labor | Line total |
|---|---|---|---|---|---|---|
| 1. Demo and haul-away1 bathroom; disposal allowance, no hazardous materials. | 1 ea | $350.00 | $350.00 | 16 hr | $1,040.00 | $1,390.00 |
| 2. Framing and wall repairMinor blocking and patching; no structural changes. | 1 ea | $425.00 | $425.00 | 10 hr | $650.00 | $1,075.00 |
| 3. Tub and drainStandard 60 in tub; existing drain location. | 1 ea | $850.00 | $850.00 | 8 hr | $520.00 | $1,370.00 |
| 4. Plumbing rough-inTub, toilet and vanity stay in place; fittings allowance. | 1 ea | $525.00 | $525.00 | 10 hr | $650.00 | $1,175.00 |
| 5. Electrical and vent fanReplace fan, light and GFCI; existing circuit and duct. | 1 ea | $275.00 | $275.00 | 6 hr | $390.00 | $665.00 |
| 6. Floor tile and setting materials8 × 10 ft floor; tile purchase includes 10% waste. | 80 sq ft | $6.00 | $480.00 | 8 hr | $520.00 | $1,000.00 |
| 7. Tub surround tile and setting materials3 walls, tiled to 8 ft; purchase includes 10% waste. | 100 sq ft | $8.00 | $800.00 | 20 hr | $1,300.00 | $2,100.00 |
| 8. Vanity, top and faucet1 standard 36 in vanity with top and faucet. | 1 ea | $950.00 | $950.00 | 6 hr | $390.00 | $1,340.00 |
| 9. Toilet1 toilet, seat, wax ring and supply line. | 1 ea | $325.00 | $325.00 | 3 hr | $195.00 | $520.00 |
| 10. Wall and ceiling paint112 sq ft paintable walls + 80 sq ft ceiling; 2 coats. | 192 sq ft | $1.00 | $192.00 | 8 hr | $520.00 | $712.00 |
| 11. Base trimExposed perimeter after tub, doorway and vanity deductions. | 20 lin ft | $4.00 | $80.00 | 4 hr | $260.00 | $340.00 |
| 12. Backer board and waterproofing1 system for 100 sq ft surround; separate from tile materials. | 1 ea | $371.33 | $371.33 | 5 hr | $325.00 | $696.33 |
- Materials
- $5,623.33
- Labor: 104 hr × $65.00
- $6,760.00
- Subtotal: materials + labor
- $12,383.33
- Markup: 20% × $12,383.33
- $2,476.67
- Sample estimate total
- $14,860.00
Markup rounds to the nearest cent: $12,383.33 × 0.20 = $2,476.666, rounded to $2,476.67.
Assumptions to check before bidding.
Where quantities come from
Every quantity here comes from the made-up scope, not measured plans or photos. The table explains each quantity.
Tile extends past the tub on both side walls: (5 + 3.75 + 3.75) × 8 = 100 sq ft.
Paintable walls use a 36 lin ft perimeter: 36 × 8 − 100 − 21 − 55 = 112 sq ft.
Deductions are the tiled surround, doorway and assumed fixture or cabinet coverage. Add the 80 sq ft ceiling for paint.
Floor tile uses the gross room area as a conservative allowance. Confirm exposed floor area during your walkthrough.
What this total leaves out
- No layout changes, structural work, hidden rot, asbestos or lead remediation.
- No permits, inspections, engineering, taxes or contingency. Add these when the actual job requires them.
- No shower glass, accessories or separate door replacement.
- Existing subfloor, supply lines, circuit and vent duct are usable. No panel upgrade or new duct run.
- Normal access and working hours. Cleanup labor is included with demo; disposal cost is a material-side allowance.
The $149 estimating service fee is separate. It is not included in this construction total.
Check the scope. Then check your rates.
A useful bathroom estimate separates quantities, material allowances and labor. It also makes missing work visible before a bid goes out.
Our planned service turns your plans or measured photos into that job sheet, using your labor rate and markup.
This sample shows the format, not a promised price for your bathroom. Uploads, payments and estimate generation are not available yet.